I have a 72" diameter base plate with 16 anchors around the circumference at a diameter of 63". When checking a shear and overturning force, the calc package from Hilti Profis Engineering shows that it is checking the entire shear force against the capacity of only one anchor and it says the anchorage is failing due to the edge condition. Why is it checking all the load against only one anchor when the breakdown of loads, the V table, clearly shows that each anchor gets a portion of the loading?
Hi Toby,
Please see page 204 of the PROFIS Engineering design guide for information on how the software calculates concrete breakout failure in shear.
Regards,
Emily
Hi Toby,
Please send your .pe file to hnatechnicalservices@hilti.com for further review.
Regards,
Emily