Embedment depth h_ef

Posted by Alicja Lesniak Borowkaover 2 years ago
Embedment depth h_ef

In the attachment I am sending two anchors that differ only in h_ef = 22 in and 24 in.
What does it mean that "Concrete side-face blowout" is not calculated for h_ef? (this point is not included in the report). In contrast to h_ef=24 in and it is equal 305%.
The actual distances of the baseplate to the concrete edge have been defined.
Thank you for your answer.

EMBEDMENT,depth,h_ef

1 Reply
Posted by Ashley Couronover 2 years ago
Hilti Verified

Hi Alicja, 


Could you please share your PROFIS .pe file to deck@hilti.com so that we may be better able to assist you? 

Regards,
Ashley

Profis engineering software

1 comment on this reply
Posted by Alicja Lesniak Borowkaover 2 years ago
Files were sent. Thank you. Regards, Alicja