2-hour head of wall detail at PEMB

Posted by JCover 2 years ago
2-hour head of wall detail at PEMB

I'm looking for a 2-hour rated head of wall detail for a gyp bd and metal stud wall terminating against a pre-engineered metal building roof. The UL detail HW-D-0528 and HW-D-0529 have all the components, however I need a 2-hour rating. Is there a way to get and EJ with an additional layer of GWB on both sides? Another detail that I looked at was UL detail CJ-D-0004. This detail won't work as standing seam roof on existing building is not a minimum of 20 gauge.

2-hour head of wall detail,HW-D-0529

1 Reply
Posted by Nathaniel Crawfordover 2 years ago
Hilti Verified

Hi JC - we can help you out here with an Engineering Judgment.

This can be requested through our online platform, the HILTI CONSTRUCTION PLATFORM (HCP). This platform will be the home for all of your Fire Protection Engineering needs, including Engineering Judgment requests. You can find more information on how to access this new platform here: https://www.hilti.com/ej (US) or https://www.hilti.ca/ej (Canada.) 

Thank you!
Nate Crawford, Lead FPE

Engineering Judgments